October 8, 2026
The Ramsey Road and Honeysuckle Avenue roundabout has a public reopening date of Oct. 5. That date is the one City Engineer Ty Kovatch gave in late August, and the city was still using it on Sept. 23. A mile away, crews close Hayden Avenue and Ramsey Road after 6 p.m. tonight and again tomorrow night to put up a spanwire traffic signal. It replaces the portable units that have been there since June.
The city calls that new signal temporary. Public Works Director Alan Soderling's August update to the City Council said it is expected to stay for about eight to 10 years.
The rest of Hayden's fall roadwork makes more sense once you see the gap between those two words. The roundabout at Ramsey and Honeysuckle is the one permanent intersection being finished this season. Most of the other work is built to hold traffic steady for years while the city buys land and waits for grant money.
Ramsey has been closed to through traffic between Hayden Avenue and Prairie Avenue, and Honeysuckle between Atlas Road and Reed Road, since the closure began on June 22. Crews were scheduled to pave the roundabout on Sept. 25 and 26, weather permitting. Sidewalks, swales and landscaping come after that.
The project has collected several dates along the way, and they measure different things:
| Milestone | Date | What it means |
|---|---|---|
| Notice to Proceed | June 18, 2026 | Contract time begins |
| Original substantial completion | Aug. 28, 2026 | First target in the contract |
| Revised after date dispute | Sept. 6, 2026 | City agreed at no added cost |
| After Change Order No. 4 | Sept. 24, 2026 | Current contract target |
| Contractor's latest schedule | Oct. 2, 2026 | Estimate cited in a Sept. 22 city memo |
| Ready for final payment | Oct. 4, 2026 | Contract paperwork milestone |
| Public reopening | Oct. 5, 2026 | The date the city has announced |
Oct. 5 is still a target. As of the Hayden Reporter's Sept. 23 coverage, Change Order No. 4 did not say whether traffic would return when the work reached substantial completion or stay off until Oct. 5.
The contractor is LaRiviere Inc. The city awarded the contract in May for $1,714,895.55. After four change orders, the approved total is $1,749,135.63. A separate Sept. 22 memo approved up to $22,000 more for Welch Comer's construction administration, which brings that engineering contract's cap to $47,500.
At the Aug. 25 regional transportation meeting, Kovatch said the roundabout was about a month behind schedule because of sewer force-main work. Change Order No. 4, which the council approved on its consent calendar in September, added 13 contract days. It lists these reasons:
The dollar side of that change order was small: $8,632.43 for 493 extra cubic yards of excavation and $949.70 for the irrigation service. City staff told the council that rejecting it would block payment for work already done and could put the city in breach of contract.
Separately, LaRiviere had argued the contract gave it 80 calendar days from June 18 rather than the Aug. 28 date in the Notice to Proceed. The city moved the original date to Sept. 6 without accepting that reading of the contract.
Taken together, the delays came from what was already in the ground: a gas line, a phone line, a sewer main, an old water service. A permanent intersection means digging down to all of them, and that is a big reason Hayden can't simply build roundabouts everywhere at once.
The temporary signal at Hayden Avenue and Ramsey Road started as a way to handle detour traffic from the roundabout closure. The version going up now is a $142,925 contract with Thorco Inc. After the two nights of closures, crews will work along the shoulders to connect power and program the signal. The city expects some minor traffic impacts and plans to finish by Oct. 7.
A roundabout for this intersection is already designed. The city's next step there is starting right-of-way negotiations. That is why the eight-to-10-year estimate is realistic. The signal covers the time it takes to buy the land and line up the money for the permanent build.
Hayden Avenue and Atlas Road is set up the same way, with one extra step first. The city plans to widen the intersection by adding three left-turn lanes: one on each Hayden Avenue approach and one on the south approach of Atlas. A temporary signal would follow. In August, the city said it hoped to finish the widening before winter shuts down local asphalt plants. If that happens, the signal could go in over the winter and be running before next summer's traffic season.
That schedule depends on a contract that hasn't been approved yet. The widening was out to bid in late August. The Sept. 29 council agenda included a right-of-way contract for the future Atlas roundabout, but no award for the widening. The roundabout itself is designed, and Soderling said the city had reached agreements on nearly all the needed properties, with one or two still unresolved. The money to build it hasn't been secured.
A third roundabout, at Hayden Avenue and Huetter Road, is still having its design finalized.
Soderling explained the order of operations to the council. Most outside funding programs won't pay for land, so a city that already owns the right of way has a stronger grant application. Money from the Hayden Urban Renewal Agency helps further because it shows a local contribution.
"Anything you can do to be ahead of somebody else" helps when grants become available, Soderling told the council.
Government Way is moving through the same steps. A traffic study of the stretch between Hayden Avenue and Prairie Avenue, done with HURA, is complete. A southbound right-turn lane at Honeysuckle is in design. A traffic light at Miles Avenue has a finished design and some of its right of way acquired. Wyoming Avenue is also on the list for a light. At the August regional meeting, the city said it had budgeted $200,000 toward a Government Way and Prairie Avenue signal. None of these has a construction date yet.
Some of the work you'll see this fall isn't about traffic. It runs on the same mix of grants and urban renewal money, though.
If the dates hold, the roundabout should be open and the Hayden and Ramsey signal running permanently by the end of next week. After that, the next things to watch are the council agendas: an award for the Atlas widening, and the remaining right-of-way agreements that decide which Hayden intersection gets the next permanent build.
How long right-of-way talks take and whether a temporary signal stays for a decade can affect what a property along Hayden Avenue, Atlas Road or Government Way is worth, both to live in and to run a business from. Joe Rosen has worked on both the building side and the real estate side in this area, and he can help you figure out what a planned intersection project means for a specific parcel. If you're weighing a property along one of these corridors, Team Rosen Real Estate is happy to look at it with you. Let's Connect.